Project status
Completed
Location
Port Kembla, NSW
Client
PKCT
Start Date
Mar 2016
Completion Date
May 2017

PKCT is the major coal facility in southern NSW for the transfer of coal from rail and road to ship. 

The objective of the Phase 2 works is to refurbish rails 3, 4 and 5 with a new improved rails system design through a multi staged process.

This multi staged remove and install process is designed to minimise through-put losses for the Port Kembla Coal Terminal whilst refurbishing this important asset.

Project scope involves:

  • undertaking detailed design, manufacture and supply of rail system supports
  • removal of existing crane rail infrastructure and installation of rails 3, 4 and 5 through six staged shutdowns
  • installation, testing and commissioning of new crane rail system
  • installation and testing of rail earthing system