Project status
Completed
Location
Bomen Road, Wagga Wagga
Client
BMD
Start Date
Mar 2017
Completion Date
Aug 2017

As a part of BMD’s $35 million Bomen Enabling Roads project in Wagga Wagga which included closing the Dampier Street level crossing and building an 18-metre-wide rail underpass, as well as constructing link roads.

Throughout the construction of the rail underpass, Martinus was responsible for:

  • safely managing live rail traffic throughout the construction phase
  • provide safe-working resources
  • track monitoring resources
  • establish track monitoring regime
  • managing signalling works to book out trackwork
  • track resources to remove and install track at each stage, track certification.