Project status
Completed
Location
Webb Dock
Client
BMD
Start Date
Aug 2015
Completion Date
Oct 2016

Martinus completed the installation of Crane Rail Systems package for BMD on the Webb Dock project in Port Melbourne.

Martinus Rail has drawn on their expertise from the delivery of previous and existing crane rail projects at Port Botany and Port Kembla in NSW.

This project comprises of:

  • 1,304m of Gantrex Slab Track – Ship to Shore (STS)
  • 5,680m of Gantrex Ballasted – Automatic Stacking Crane (ASC) track

This is a unique project for Martinus Rail and BMD where the Ballasted ASC Gantrex System is one of only 4 in the world.

The project team is working very closely with the client, designers and Gantrex to deliver this bespoke system and has successfully completed the first phase of the project.